Post by James Fleshner on Apr 5, 2007 11:34:20 GMT -5
|
|
|
Post by James Fleshner on Apr 5, 2007 11:43:17 GMT -5
This is a 981 sheet hang and finish and paint job for a medical center.
|
|
turk
New Member
Posts: 7
|
Post by turk on Apr 5, 2007 16:20:42 GMT -5
I noticed in your pics that you guys dont put fastners on the top sheets (3-4 inchs down) is this to keep it from cracking? I have done this for other contractor.
Almost a tousand sheets thats a good size job. How many employees do you have?
Those door frames are a pain in the A$$ to hang around.
Are you guys busy down your way? It has been pretty slow up here.
|
|
|
Post by James Fleshner on Apr 5, 2007 17:32:36 GMT -5
We usually nail the tops
I Have 7 guys and myself on this hang
We stay fairly busy, but we are starting to slow a bit here.
|
|
|
Post by James Fleshner on May 3, 2007 9:03:55 GMT -5
I usually run two 3 men crews on the lids until they are all done, then go to two men crews on walls. This hang was all 5/8 type x board.Its been a good job to work on.
|
|